PWW Core – Nashua

My Water System Documents and Details

City : Nashua , Water System : PWW Core – Nashua

Current Water Quality Report Name

Current-Water-Quality-Report.pdf

Water Restriction

No Restrictions

Water Restriction Last Update

Monday, April 4, 2022

Flushing

Night flushing will occur between 10:00 pm and 6:00 am on Sunday, October 9th, 2022; we will continue with day flushing between the hours of 6:00 am and 4:00 pm on October 10th, 2022.

Construction/Projects Update

Kessler Farm Water Storage Tank Project:

The Kessler Farms Tank is back in operation. After the tank was placed back into operation there were some flow reversals that caused discolored water in the area between the tank and Amherst St. Extensive water main flushing by our Distribution Department resolved the problem. The contractor, DN TANKS, and its subcontractors are presentlyin and out of the tank site to complete landscaping, fence insallation, adn cvarious other project closeout tasks. No shutdowns are planned and none of the remaining work requires and interruption of water service.

If any problems arise, customers in the Kessler Farm Condominium development should contact their property management representatives. They will then report the issues to our customer service team and field personnel will be dispatched to address the issue. Customers outside the Kessler Farm Condominium development should contact Pennichuck directly to have water issues addressed.

If you have any questions or concerns about the work effort to replace the Kessler Farm water storage tank please contact the Distribution Engineer Manager, Pete Tedder, at (800)553-5191 ext. 2324 or the Project Engineer, Ryan Houle, at (800)553-5191 ext. 2367.

Coburn Woods Water Main Replacements:

Our contractor, RWC Enterprises, recently completed final street overlay and landscaping repairs. RWC will also be installing special fittings at most of the remaining 23 street entrances off the maon Coburn Woods Road so water main replacements can resume in 2024 or 2025

Progress meetings will be scheduled once a firm return date is established. Please contact your association president if you have any concerns that need to be addressed.

If you have questions or concerns about the work effort to replace the water mains in Coburn Woods, please contact the Distribution Engineering Mannager, Pete Tedder, at (800)553-5191 ext. 2324 or the Project Engineer, Ryan Houle, at (800) 553-5191 ext. 2367.

2021 SEWER RELATED WATER MAIN REPLACEMENTS:

This is a water main replacement effort that is being undertaken in coordination with thte city of Nashua's sewer replacement/repair program and the city of Nashua's paving program.

The contract was awarded to Defelice Corporation. It was intended that work would begin in August 2021. Unfortunatly work was delayed due to covid related supply chain issues. Simply put, new pipe was not available. Pipe began arriving in December 2021 though it arrived too late to start with the replacement effort.

Work began towards the end of May 2022 and involves the following streets: Miami Street, Kendrick Street, Faxon St, and Faxon Avenue.

So far, DeFelice has transferred all streets to a temporary water main and has completed the main installation on Miami Street, Faxon Street, and Faxon Avenue. Water service reconnections on said streets are underway. The city of Nashua is completing sewer repair/replacement work on Kendrick Street by approximately 6/23/22. Once that is complete, DeFelice will be able to install the new water main on Kendrick street.

If you have questions or concerns about the sewer related water main replacement project, please contact the Distribution Engineering Manager, Pete Tedder, at (800)553-5191 ext. 2324 or the Project Engineer, Ryan Houle, at (800)553-5191 ext.2367

2022 Small Diameter Water Main Replacements - North:

This is a water main replacement effort that is being undertaken in coordination witht the city of Nashua's paving program. Pennichuck's contractor for this effort is S.U.R. West, Inc.

Work is well in progress. The following streets have been completed:Chautauqua Avenue from Broad Street to the end, Pine Hill Avenue from Wright Road to the west end, and French Street mains and service reconnections have been completed. There have been multiple shutdowns required for this work and we appreciate the understanding of the affected customers. Mount Pleasant Street from Abbott Street to Manchester Street still needs to be completed. SUR West is still waiting on materials for said section.

If you have any questions or concerns about the 2022 Small Diameter Water Main Replacement Project - North, please contact the Distribution Engineer Manager, Pete Tedder, at (800)553-5191 ext.2324 or the Project Engineer, Ryan Houle at (800)553-5191 ext.2367

2022 Small Diameter Water Main Replacements - South

This is a water main replacement effort that is being undertaken in coordination witht the city of Nashua's paving program. Pennichuck's contractor for this effort is Joseph P. Cardillo & Son, Inc.

The following streets will be affected by the project: Dudley Street, Niquette Drive, Nye Avenue, and Ledgeewood Hills Drive. Cardillo has not come to town yet because that are still waiting on some materials' deliveries. Work is expected to begin mid-late July 2022

If you have any questions or concerns about the 2022 Small Diameter Water Main Replacement Project - South, please contact the Distribution Engineer Manager, Pete Tedder, at (800)553-5191 ext.2324 or the Project Engineer, Ryan Houle at (800)553-5191 ext.2367